Step-By-Step Foundations
|
 Simple
Solution For Uneven Ground |
|
1/
Prepare
Your Site For Construction
Before
receiving
your garden shed or
gazebo, clear the construction area. Remove all debris, roots, grass and
rocks.
Make sure the ground slopes away from the site at least 10 feet in all
directions. If necessary, build up the soil in the center of the site and
slope away for the high point to provide drainage. Fill in any low spots
within the perimeter of the site. A slope of 1/8 inch per foot is enough to
prevent water accumulation.
We recommend excavating the site 4 inches deep and laying gravel or crushed
rock where drainage may be a concern.
2/ Laying Out The Foundation
No
matter which type of foundation you’ve chosen, start by outlining the
"footprint" on the site. Start by choosing one corner of the garden shed or
the center of gazebo and mark it (A) by driving a stake into the ground.
GARDEN SHEDS
Stretch a line
from stake A straight across C and fasten it to a temporary stake outside
the intended garden shed area. Measure along this line from A and mark the
garden shed dimension in that direction. Drive a stake there and set up
batter boards. Use the 3-4-5 triangulation method to extend another line at
right angles to the A-C line. Measure to the next corner and stake it.
Continue until all corners of the garden shed are connected by right angle
lines.
3-4-5 Triangulation Method
Measure
along the line 3 feet from the first stake A, and mark the string at this
point. From stake A, run a second line perpendicular to the first. Measure
out 4 feet to locate point C. If this second line is exactly at a right
angle to the first, the diagonal line between A & C will be 5 feet. If not,
move point C left or right until the diagonal measures 5 feet and stake
that point.
 |
| |
|
|
| |
LAYING OUT THE FOUNDATION
1. Mark one corner of the proposed shed by
driving a temporary stake, then set temporary batter boards at
right angles to each other to provide support for guidelines. |
 |
| |
10 |
|
|

| |
|
|
| |
LAYING OUT THE FOUNDATION
2. Run a line across two stakes. Measure from
point A on the first stake along this line 3 ft. and mark point
B. |
 |
| |
10 |
|
|

| |
|
|
| |
LAYING OUT THE FOUNDATION
3. Run a second line perpendicular to the first
across point A. Mark point C 4ft. from point A. Move line AC so
that the distance BC is exactly 5 ft. Angle BAC is now 90
degrees. |
 |
| |
10 |
|
|

| |
|
|
| |
LAYING OUT THE FOUNDATION
4. Set up batter boards and guide lines to
outline the entire shed, making right angles at each corner
using the 3-4-5 triangle method described in step 3. |
 |
| |
10 |
|
|
GAZEBOS
Stretch a radial
line from center stake A. Calculate the radius by using 1/2 the diameter of
gazebo. Using orange spray paint or something similar, mark out a circle.
First determine door location by using one Rim Joist of Gazebo, stake
points where rim joist intersects circle. Move around circle staking out
all intersecting points until all corners are connected.
3/ Determine The Type
Of Foundation

1. PATIO STONE FOUNDATION
If
the ground is stable and has sufficient drainage, you can set patio stones
directly on firm, compacted soil. If not, lay on gravel or crushed rock as
previously described.
GARDEN SHEDS:
Starting with one floor
section, position stones around its perimeter and specific joists. (For
details, see specific instruction manual) Use a 2x4 straight piece of
lumber on edge and a carpenter’s level to position correctly. Add or remove
soil/sand under each stone until level. Complete remaining floor sections
in the same manner. When all floor panels are level with each other, flip
over, screw together and place back on level foundation.
GAZEBOS:
Position patio stones
on outline of gazebo previously described. For details of how and where
stones go, see specific instruction manual. Use a 2x4 straight piece of
lumber on edge and a carpenter’s level to position correctly. Add or remove
soil/sand under each stone until level. When stones are level, position
completed sub-structure (Rim, Long & Short Joist and Core Block) on top.
Once again, use a level to confirm positioning and make any necessary
adjustments.
2. 4x4 PRESSURE TREATED BEAM FOUNDATION
You
can build directly on pressure-treated beams or railroad ties laid on a
properly prepared construction site. Run beams perpendicular to floor
joists. Use a 2x4 straight piece of lumber on edge and a carpenter’s level
to position correctly.
To prevent the beams from shifting, secure them with a 1/2" inch rebar
inserted through holes drilled in the beams and driven 3 to 4 feet into the
ground. Leave each side or end of the foundation open to promote drainage
and air circulation beneath the floor.

| |
|
|
| |
4x4 PRESSURE TREATED FOUNDATION
This simple foundation consists of pressure
treated beams laid directly on compacted gravel base. Use 1/2 "
rebar to prevent beams from shifting. Joists are attached to
beams with 16d galvanized nails. |
 |
| |
10 |
|
|
3. CONCRETE SLAB FOUNDATION
Typically
a slab 3-4 inches thick laid over a sub base of 4 inches of gravel or
crushed rock is sufficient but may vary depending on your geographic
location.
Using either mix your own concrete of having it delivered by truck, ready
to pour, depends on how much time and effort you have to dedicate to the
project. A slab for our 8x10 foot Rancher or a 10 foot gazebo both to a
depth of 4 inches will require approximately 1 cubic yard of premixed
concrete.
Use the following
procedure:
1. Excavate the slab area and footing trench.
2. Excavate the slab area to a depth 6 inches. This would put the finished
slab surface 2 inches above ground (4 inches of gravel)
3. Set up your batter board strings to represent the outside face of the
slab. At each corner, drop a plumb line from the intersecting strings to
the bottom of the trench, then drive a 2x4 stake at this point. Using the
plumb bob again, drive a nail into the top of the stake where the plumb bob
touches it. Attach strings between the stakes. Using the strings as guides,
drive the 2x4 form stakes around the trench perimeter, spaced on 2 foot
centers.
4. Attach the form boards to the stakes with double-headed nails. Make sure
the stakes are on the outside of the boards and flush with or below them.
5. Use 2x4 stakes to brace the corners of the forms.
6. Backfill the excavation with 4 inches of gravel, then lay down a plastic
vapor barrier.
7. Spread or pour concrete with a rake or hoe, compacting it gently into
the footing areas. Use a shovel to move concrete into footing trench. Make
the pour to about 1 inch above the forms to allow for settling. Use a long
2x4 to level the concrete. Move the board in a side-to-side motion as you
pull it towards you.
8. Use finishing tools, such as a bull float and trowel, to smooth the
concrete surface. Allow the concrete to cure fully (seven to ten days).

| |
|
|
| |
CONCRETE SLAB FOUNDATION
1. Backfill excavation with gravel; install
vapor barrier. |
 |
| |
10 |
|
|

| |
|
|
| |
CONCRETE SLAB FOUNDATION
2. Pour concrete into the forms, and spread it
with a rake or shovel. Use a long 2x4 to screed the concrete
level. |
 |
| |
10 |
|
|

| |
|
|
| |
CONCRETE SLAB FOUNDATION
3.Use finishing tools, such as a bull float and
trowel, to smooth the concrete surface to the desired finish. |
 |
| |
10 |
|
|
|