Foundation Preparation for Sheds

Preparing your site for Sheds, Greenhouses, Playhouses, Gazebos

   
Recommended methods for constructing basic foundations for sheds, greenhouses, playhouses etc:
• Patio Stones
• 4x4 Pressure Treated Beams
• Concrete Slab
Step-By-Step Foundations
Simple Solution For Uneven Ground

1/ Prepare Your Site For Construction
Before receiving your garden shed or gazebo, clear the construction area. Remove all debris, roots, grass and rocks.

Make sure the ground slopes away from the site at least 10 feet in all directions. If necessary, build up the soil in the center of the site and slope away for the high point to provide drainage. Fill in any low spots within the perimeter of the site. A slope of 1/8 inch per foot is enough to prevent water accumulation.

We recommend excavating the site 4 inches deep and laying gravel or crushed rock where drainage may be a concern.

2/ Laying Out The Foundation
No matter which type of foundation you’ve chosen, start by outlining the "footprint" on the site. Start by choosing one corner of the garden shed or the center of gazebo and mark it (A) by driving a stake into the ground.

GARDEN SHEDS
Stretch a line from stake A straight across C and fasten it to a temporary stake outside the intended garden shed area. Measure along this line from A and mark the garden shed dimension in that direction. Drive a stake there and set up batter boards. Use the 3-4-5 triangulation method to extend another line at right angles to the A-C line. Measure to the next corner and stake it. Continue until all corners of the garden shed are connected by right angle lines.

3-4-5 Triangulation Method
Measure along the line 3 feet from the first stake A, and mark the string at this point. From stake A, run a second line perpendicular to the first. Measure out 4 feet to locate point C. If this second line is exactly at a right angle to the first, the diagonal line between A & C will be 5 feet. If not, move point C left or right until the diagonal measures 5 feet and stake that point.

 

 
 
  LAYING OUT THE FOUNDATION 1. Mark one corner of the proposed shed by driving a temporary stake, then set temporary batter boards at right angles to each other to provide support for guidelines.
  10  



 

 
 
  LAYING OUT THE FOUNDATION 2. Run a line across two stakes. Measure from point A on the first stake along this line 3 ft. and mark point B.
  10  



 

 
 
  LAYING OUT THE FOUNDATION 3. Run a second line perpendicular to the first across point A. Mark point C 4ft. from point A. Move line AC so that the distance BC is exactly 5 ft. Angle BAC is now 90 degrees.
  10  



 

 
 
  LAYING OUT THE FOUNDATION 4. Set up batter boards and guide lines to outline the entire shed, making right angles at each corner using the 3-4-5 triangle method described in step 3.
  10  


GAZEBOS
Stretch a radial line from center stake A. Calculate the radius by using 1/2 the diameter of gazebo. Using orange spray paint or something similar, mark out a circle.
First determine door location by using one Rim Joist of Gazebo, stake points where rim joist intersects circle. Move around circle staking out all intersecting points until all corners are connected.


3/ Determine The Type
Of Foundation


1. PATIO STONE FOUNDATION
If the ground is stable and has sufficient drainage, you can set patio stones directly on firm, compacted soil. If not, lay on gravel or crushed rock as previously described.

GARDEN SHEDS: Starting with one floor section, position stones around its perimeter and specific joists. (For details, see specific instruction manual) Use a 2x4 straight piece of lumber on edge and a carpenter’s level to position correctly. Add or remove soil/sand under each stone until level. Complete remaining floor sections in the same manner. When all floor panels are level with each other, flip over, screw together and place back on level foundation.

GAZEBOS:
Position patio stones on outline of gazebo previously described. For details of how and where stones go, see specific instruction manual. Use a 2x4 straight piece of lumber on edge and a carpenter’s level to position correctly. Add or remove soil/sand under each stone until level. When stones are level, position completed sub-structure (Rim, Long & Short Joist and Core Block) on top. Once again, use a level to confirm positioning and make any necessary adjustments.


2. 4x4 PRESSURE TREATED BEAM FOUNDATION
You can build directly on pressure-treated beams or railroad ties laid on a properly prepared construction site. Run beams perpendicular to floor joists. Use a 2x4 straight piece of lumber on edge and a carpenter’s level to position correctly.

To prevent the beams from shifting, secure them with a 1/2" inch rebar inserted through holes drilled in the beams and driven 3 to 4 feet into the ground. Leave each side or end of the foundation open to promote drainage and air circulation beneath the floor.


 

 
 
  4x4 PRESSURE TREATED FOUNDATION This simple foundation consists of pressure treated beams laid directly on compacted gravel base. Use 1/2 " rebar to prevent beams from shifting. Joists are attached to beams with 16d galvanized nails.
  10  



3. CONCRETE SLAB FOUNDATION
Typically a slab 3-4 inches thick laid over a sub base of 4 inches of gravel or crushed rock is sufficient but may vary depending on your geographic location.

Using either mix your own concrete of having it delivered by truck, ready to pour, depends on how much time and effort you have to dedicate to the project. A slab for our 8x10 foot Rancher or a 10 foot gazebo both to a depth of 4 inches will require approximately 1 cubic yard of premixed concrete.


Use the following procedure:
1. Excavate the slab area and footing trench.

2. Excavate the slab area to a depth 6 inches. This would put the finished slab surface 2 inches above ground (4 inches of gravel)

3. Set up your batter board strings to represent the outside face of the slab. At each corner, drop a plumb line from the intersecting strings to the bottom of the trench, then drive a 2x4 stake at this point. Using the plumb bob again, drive a nail into the top of the stake where the plumb bob touches it. Attach strings between the stakes. Using the strings as guides, drive the 2x4 form stakes around the trench perimeter, spaced on 2 foot centers.

4. Attach the form boards to the stakes with double-headed nails. Make sure the stakes are on the outside of the boards and flush with or below them.

5. Use 2x4 stakes to brace the corners of the forms.

6. Backfill the excavation with 4 inches of gravel, then lay down a plastic vapor barrier.

7. Spread or pour concrete with a rake or hoe, compacting it gently into the footing areas. Use a shovel to move concrete into footing trench. Make the pour to about 1 inch above the forms to allow for settling. Use a long 2x4 to level the concrete. Move the board in a side-to-side motion as you pull it towards you.

8. Use finishing tools, such as a bull float and trowel, to smooth the concrete surface. Allow the concrete to cure fully (seven to ten days).


 

 
 
  CONCRETE SLAB FOUNDATION 1. Backfill excavation with gravel; install vapor barrier.
  10  



 

 
 
  CONCRETE SLAB FOUNDATION 2. Pour concrete into the forms, and spread it with a rake or shovel. Use a long 2x4 to screed the concrete level.
  10  



 

 
 
  CONCRETE SLAB FOUNDATION 3.Use finishing tools, such as a bull float and trowel, to smooth the concrete surface to the desired finish.
  10  


 

 

 

Contact Us | Privacy Policy | Legal Info | Links | Customers Say... | Catalog

Can't find what you are looking for?     Us,
or you can call us Toll Free: 888-
751-0101

Hours of Operations

August-Feb: 9am-5pm Weekdays.  Closed Weekends
March-July: 9am-7pm Weekdays & 10am-3pm Saturdays.

All times are Central Time

 
© Copyright 2001-2008 by BackyardCity.com.  All Rights Reserved.
Site maintained by VIMATA Interactive, Inc.

Search Engine Optimization Services & Internet Marketing - CommerceFriends.com

Images Disclaimer:  We have made a concerted effort to provide images that accurately represent the actual color, style, size & shape of each product.  However, due to all the possible variants, including but not limited to: light source, monitor quality or settings, etc.; we can not guarantee that these images represent the actual colors of the product.  Returns due to color discrepancies will be considered a return of a non-defective item as detailed in our Legal Policies.

     
 
Last Updated: 01/18/2008 12:08 PM - ID:2512

Related Terms: Playhouses, Site Preparation, Gazebos, Foundation, Sheds, Storage Sheds
Patio Furniture, Outdoor Umbrellas
888-751-0101

Search Our Site

HACKER SAFE certified sites prevent over 99.9% of hacker crime.